Downtown Manchester

Starting from £185,000

DESCRIPTION

An energetic community at the gateway to Manchester, providing a spacious range of 368, one, two and three bedroom apartments.

The development will provide the luxury of concierge, a wealth of high grade private realm and communal roof terraces incorporating outdoor kitchens and ‘chill out’ zones. Dried and chilled post rooms ensure you don’t have to be at home to take receipt of goods or perishable food store deliveries as Downtown’s designated concierge will take care of it.

Rapid reactive on site maintenance and coordinated support provides piece of mind for hassle free living and large service lifts ensure moving in is trouble free. Biometric and monitored entry provides a more secure living experience.

Relieve the stresses of a working day in our on site fitness suite, steam room or plunge-pools or relax in our spacious lobby or even enjoy a movie in our state of the art media room.

If working from home is becoming too much, adjourn to our business centre or make use of Downtown’s onsite boardroom and enjoy unrestricted high speed broadband access throughout the property.

INVESTMENTS HIGHLIGHTS
  • 368 apartments.
  • 1, 2 and 3 bedroom.
  • SPA – steam room, plunge pools.
  • High tech gymnasium.
  • Full service concierge.
  • Cinema room.
  • Business centre.
  • 5 minute walk into the City Centre.
  • 6% rental yields.
  • Chill out roof terraces.

Nestled on the banks of the River Irwell, footbridge access provides a direct link to the vibrant centre of Manchester’s booming city within five minutes.

Step 1 – Choose an Apartment

Step 2 – Complete Reservation form

Step 3 – £5,000 Reservation fee

Step 4 – 30% on Exchange (Minus £5,000 reservation fee)

Step 5 – 70% on Completion

  • Phase 1
    Civil Operations

    • Contig walls and capping beam – completed
    • Pile caps and beams – completed
    • Lift shafts (Subs) incl. cores – completed
    • Drainage and services – completed
    • Form, rebar and concrete basement slab – completed
  • RC Operations
    • Walls, Columns and cores have commenced in the period to blocks D – F
    • Transfer Deck to Block D podium has commenced
  • General activities
    • Erection of tower crane 2 scheduled for 26.11.17
  • Phase 2
    Civil Operations

    • Contig walls and capping beam – completed
    • Pile caps and beams – ongoing
    • Lift shafts (Subs) incl. cores – ongoing
    • Drainage and services – ongoing
    • Prep basement slab – ongoing
    • Main sewer outfall connection – complete
  • Phase 2
    Civil Operations

    • Erection of tower crane – completed
    • Main site set up – complete

Next update due WC 27th February 2018