Axis Tower Manchester

 

 

  • All site enabling works completed 23/12/2016
  • Temporary incoming utilities connected
  • Excavation to bearing strata completed across the building
    footprint and any existing ground obstructions removed
  • Concrete blinding to Lower Ground Floor slab completed by concrete sub-contractor
  • Reinforcement works to Lower Ground Floor slab commenced in
    readiness for main concrete pour
  • Proposed drainage layout works commenced
  • Temporary loading platform works to Whitworth Street West
    commenced, piled, reinforced and concrete poured
  • Next update due – WC 24th April 2017