June 2019 Construction Update

Works on the external façade of Axis are now complete with the exception of the final section on the Whitworth Street elevation.

Infill of hoist affected apartments has commenced with partitions being fixed and bathrooms being fitted up to the 26th floor.

Kitchens are being fitted up to the 25th floor whilst the crash deck over the canal has been removed.

Next update due week commencing 23rd September 2019