Downtown

Downtown Construction Updates

SOLD OUT

Estimated Yields

7%

Apartments

368

Bedrooms

1, 2, 3

PHASE ONE (Blocks D, E, F)

Block D

  • Concrete frame now complete
  • Mechanical & Electrical first fix complete up to level 7
  • Boarding to apartments upto level 9
  • Skimming level 7
  • Second fix joinery has commenced level 7
  • Kitchens installation complete up to level 4
  • Second fix sanitary ware installation complete up to level 2&3
  • Decoration complete up to levels 3
  • Lift installation in progress
  • Vinyl flooring preparation up to level 3

Block E

  • Skimming complete up to level 3
  • Second fix joinery complete up to level 3
  • Kitchens installation complete up to level 2
  • Second fix sanitary ware installation complete up to level 2
  • Decoration levels 2 ongoing
  • Ceramic tiling Preparation up to level 3

Block F

  • Mechanical & Electrical first fix apartments complete up to level 6
  • Boarding to apartments complete up to level 7 – ongoing
  • Plastering level 3 – ongoing.
  • Lift installation – complete.

PHASE TWO (Blocks A, B, C)

  • Concrete frame has now progressed to the 11th
  • Concrete Frame will be completed by December 2018

Next update due WC February 2019

November 2018
August 2018
May 2018
February 2018
November 2017
October 2017
August 2017
April 2017
Downtown
  • This field is for validation purposes and should be left unchanged.