February Construction Update 2019

Phase 1 – Block D, E and F

  • Skimming level 9 completed
  • Second fix joinery completed
  • Kitchen installations completed
  • Second fix Sanitary ware installed up to level 6
  • Decoration finalised up to level 6
  • Mist Coat completed to apartments
  • Ceramic tiling completed
  • Vinyl flooring preparation completed up to level 8
    Snagging now in progress

Block E

  • Complete with snagging in progress

Block F

  • Levels 1 – 3 complete
  • Decoration and final fix joinery progressing well on levels 4 to 6

Phase 2 (Blocks A,B and C)

  • Concrete frame completed
  • Steel Frame systems A,B & C now being installed
  • Screed to ground floor ongoing
  • Party walls & corridors ongoing to A,B & C
  • Roof works to block C ongoing
  • Mechanical & Electrical systems installation ongoing
  • Ramp works ongoing

February 2019
November 2018
August 2018
May 2018
February 2018
November 2017
October 2017
August 2017
April 2017