Downtown

Downtown Construction Updates

Starting From

£185K

Estimated Yields

7%

Apartments

368

Bedrooms

1, 2, 3

Next update due week commencing 27th May 2018

The main civil operations up to and including basement car park slab and associated drainage have now been completed, with the concrete Frame commencing within the reporting period.

Phase I

  • Block D - 3rd floor completed
  • Block E - 1st floor completed, walls and columns 1st to 2nd floor currently progressing
  • Block F - 1st floor completed, walls and columns 1st to 2nd floor currently progressing

Phase II

  • Civil operations to basement completed
  • Basement walls, columns and cores progressing
  • Podium slab progressing
  • The concrete frame operations are currently taking a two week period to commence and complete each floor.
February 2018
November 2017
October 2017
August 2017
April 2017
Downtown