Downtown

Downtown Construction Updates

SOLD OUT

Estimated Yields

7%

Apartments

368

Bedrooms

1, 2, 3

Block D

  • Sedum roof 75% -  complete
  • Structural Steel Framing System to perimeter block -  complete
  • Windows and curtain walling continuing up to level 9 - ongoing
  • Louvres and brick panels in the period up to level 7 - ongoing
  • Mechanical & Electrical  first fix corridors (sprinklers & flat duct) Level 7 – ongoing
  • Mechanical & Electrical first fix apartments level 2 – ongoing
  • Boarding to apartments level 2 – ongoing
  • Skimming of boards at level 1 – commenced

Block E

  • 1st Fix Mechanical & Electrical corridors (sprinklers & flat duct) -  complete
  • 1st Fix Mechanical & Electrical level 1  - complete
  • Windows – complete
  • Cladding 60%  - complete

Block F

  • Structural Steel Framing System to perimeter of block  - complete
  • Sedum Roof  - complete
  • Window & Curtain walling continuing on levels 6&7 - ongoing
  • Cladding levels Ground Floor to level 3 - ongoing

Phase 2

  • Podium deck  -  complete
  • Reinforced concrete frame for Podium to 1st Floor  - complete
  • Reinforced concrete frame for walls and cores to level 2  - complete
  • Reinforced concrete frame floor to level 3 & part 4 70%  - complete
  • Reinforced concrete frame walls & cores level 3-4 20%  - complete

Next update due WC 26th November 2018

August 2018
May 2018
February 2018
November 2017
October 2017
August 2017
April 2017
Downtown

  • This field is for validation purposes and should be left unchanged.