Downtown

Downtown Construction Updates

Starting From

£185K

Estimated Yields

7%

Apartments

368

Bedrooms

1, 2, 3

Phase One (Structure)

Block D

  • 8th Floor completed
  • 8th – 9th Floor : Walls, Columns and Cores currently being progressed

Block E

  • All concrete frame operations are complete

Block F

  • 6th Floor completed
  • 6th – 7th Floor : Walls, Columns and Cores currently being progressed

Phase One Block D, E & F – (External Façade / Internal Operations)

Block D

  • SFS Ground –  6th Floor complete
  • External Board, membrane, tape and insulate Ground – 4th Floor complete
  • External windows and curtain walling Ground to 3rd Floor complete.
  • Internal setting for partitions and 1st fix operations Ground – 4th Floor complete
  • 1st fix Mechanical & Electrical Ground – 1st Floor commenced
  • Internal metalwork (partitions) commenced

Block E

  • SFS 100% complete
  • External Board, membrane, tape and insulate Ground – 1st Floor ongoing

Block F

  • SFS Ground – 4th Floor completed
  • External Board, membrane, tape and insulate Ground – 1st Floor ongoing

Phase Two  - Blocks A, B &  C

  • Structure up to & including Podium deck completed
May 2018
February 2018
November 2017
October 2017
August 2017
April 2017
Downtown

  • This field is for validation purposes and should be left unchanged.