February 2019 Construction Update

  • Works are on programme
  • Construction of the pool structure is complete
  • The slip form rig construction is complete and the stair and lift core construction between Tower 1 and 2 is underway
  • The base to the Tower 2 core is complete
  • Tower 3’s pile cap foundations and drainage is underway