parkgate_logo_landscape

Park Gate

Luxury living in a parkside location

Starting From

£125K

Annual Rental Yields

6%

Apartments

126

Bedrooms

1 & 2

Featuring 126 luxury studio, one bedroom and two bedroom apartments, Park Gate at Lyndon Place brings together suburban comfort and urban convenience in one of the UK’s fastest growing cities. The development has excellent transport links to Birmingham city centre and is in a prime position to benefit from the new High-Speed Rail Network (HS2).

  • Parkside location
  • Excellent transport links
  • HS2 development nearby
  • Close proximity to the airport, city centre and NEC
  • High rental yields
  • Manned concierge
  • Onsite gym
  • Overlooking Sheldon Park
Development Overview

Combining fresh outdoor space, luxury finishes and all of the essentials for modern living, Park Gate perfectly blends suburban life with urban excitement in one of the UK’s fastest growing cities. With each apartment finished to an impeccable standard, residents will have everything they need to relax, unwind and entertain. Park Gate’s location gives the development excellent access to the new High-Speed Rail network, as well as great transport links into Birmingham city centre and beyond.

Payment Process

Step 1 – Choose an Apartment

Step 2 – Complete Reservation form

Step 3 – £5,000 Reservation fee

Step 4 – 30% on Exchange (Minus £5,000 reservation fee)

Step 5 – 70% on completion

Construction Updates

June Construction Update 2019

Demolition works to the roof are on-going for the old Lyndon Place development in the east and west wings. The 4th floor east demolition works are now nearing completion, with the metal stud party walls now in position. The 4th floor west demolition works are now complete with the metal stud walls now under construction.

Across the development site, first fix plumbing works and electrics are ongoing, with further floors undergoing the following:

  • Third floor west: metal stud partitions ongoing
  • Second floor east: demolition works ongoing
  • Second floor west: metal stud partitions ongoing
  • First floor east: demolition works ongoing
  • First floor west: demolition works ongoing and metal stud walls started

Demolition works have also begun in the basement, with scaffolding to the west wing and east wing erected.

The cleaning of the brick work on the west wing rear elevation has now been completed with works starting on the front elevation. Canopy works are currently ongoing with the main canopy works to begin shortly.

 
 
 
Next update due week commencing 23rd September 2019
 

 