Next update due week commencing 27th May 2018

  • Phase 1 metsec and Phase 2 steel frames are complete
  • The roof is completed
  • All windows on Phase 1 are installed. Window installation for Phase 2 ongoing.
  • The brick work is completed on Phase 1.
  • 12 brick work courses completed on Phase 2
  • 1st fixings completed on Phases 1 and 2
  • Plastering on floors 1-3 completed
  • Mist coating commencing on 26th February
  • Lift shaft completed from ground floor to 2nd floor. Currently progressing 3rd to 4th floor.
  • Tower crane comes down on 26th February.
  • Overall strong progress and meeting programme milestones.