Northgate Studios

Northgate Studios
Construction Updates

SOLD OUT

Estimated Yields

8%

Apartments

150

Bedrooms

Studios

Next update due week commencing 27th August 2018

External:

  • Scaffold stripped on phase one courtyard (see pic)
  • Remaining Scaffolding will be taken down within next 4 weeks

Internal – phase 1:

  • Flooring completed on floors 1,2,3 and 4
  • Kitchens installed on floors 1,2,3 and 4
  • Painting – 1st and second coat completed on levels 1,2,3 and 4. Waiting final coat

Internal – phase 2:

  • Windows fitted up to 4th floor
  • All bathroom pods fitted
  • Pre-plaster inspections approved to 4th floor
  • Final boarding commenced on floors 1 – 3
May 2018
February 2018
November 2017
August 2017
June 2017