The Laceworks Construction Updates

SOLD OUT

Estimated Yields

7.75%

Apartments

222

Bedrooms

Studios

  • Piling and groundworks complete
  • Steel and metzec frame phase 1 complete, phase 2 underway
  • Stair and lift cores progressing
  • Upper floor installation following up being the frame
  • Scaffolding erected and lower level external wall construction has commenced
  • Work remain on programme to Complete end of August 2019

Next update due WC 26th November 2018