June Construction Update 2019

At our Nottingham student development, The Laceworks, the building superstructure is now 100% complete. Brickwork on the outer skin of the external walls is progressing as per the programme, with over 50% of these works completed.

Internal fit-out is progressing well with the final fit-out of the first floor nearing completion. Works will continue up the building to allow for snagging of rooms prior to practical completion. The lettings show unit is now complete and all works are on track for the projected completion date.

Next update due week commencing 23rd September 2019